Dog pound build costs blow out by $229k

5:43 pm on 27 June 2022

Carterton District Council's [CDC] new dog pound is tracking to cost $229,000 more than the approved budget.

brown dog

Photo: Lucrezia Carnelos / Unsplash

Councillors will be asked on Wednesday whether they wanted to proceed, defer, or change the project, which had an original budget of $350,000 from the 2019/20 Annual Plan process and an approved budget of $370,000 last year.

Construction has not yet begun, with only groundworks and drafting of architectural plans completed at a cost of $46,000.

no metadata

A recent review of the project found that contingencies and fit-out costs had not been included in the approved budget, and construction costs had risen significantly since then.

Despite council staff changing the dog pound designs to reduce the new cost estimate by $80,000, the project estimate was now $599,000 - inclusive of a 20 percent contingency.

The design changes included reducing the dog pound size from 152 to 110 metres squared, and removing loading bays and toilet facilities.

In a report to council, CDC's planning and regulatory services manager Solitaire Robertson said elected members had three options: proceed with the project as is, defer the project indefinitely, or change the design further.

Additional capital costs would be funded through reserves.

Option 1 would require an additional $229,000 and would mean a building consent application could be lodged shortly.

Option 2 would defer the facility for funding in the next Long Term Plan. In the meantime, the existing facility would need urgent remedial work, which would cost $50,000.

The existing facility is no longer fit for purpose and does not meet the current legislative requirements. It would remain a risk until the new facility was built.

Option 3, recommended by council officers, was to further change the pound plan to "fit within an existing cookie-cutter style design" such as a "Totalspan building".

This would cost an additional $179,000 on top of the existing $370,000 budget.

"If approved, staff will reset the project design and elements before submitting a building consent," Robertson said.

"We will continue to engage with South Wairarapa District Council should they wish to participate in this animal shelter."

Solar power would come at an additional cost of up to $47,000 and rainwater collection and filtration would cost up to $20,000.

Council staff recommended these options be included in the facility but funded through the government's Three Waters Better Off grants.

CDC chief executive Geoff Hamilton said council officers were following through on their commitment to elected members "by letting them know before proceeding on a project whether it can be completed within the original proposed budget".

"The original $350,000 was an estimate from 2019 for the building construction, whereas the new figure is an updated estimate which includes the fit-out and a 20 percent contingency," he said.

"This gives elected members the opportunity to make an informed decision before beginning construction."

Local Democracy Reporting is Public Interest Journalism funded through NZ On Air

Get the RNZ app

for ad-free news and current affairs