Auckland Harbour Bridge's new strut successfully installed

9:21 am on 4 October 2020

The damaged Auckland Harbour Bridge was due to reopen around 9am, after being closed for repairs overnight.

No caption

Engineers still need to carry out tension work before all lanes on the bridge can be operational. Photo: RNZ / Katie Todd

The Transport Agency Waka Kotahi says a new permanent strut to replace the one that was buckled by an overturned truck two weeks ago, has been successfully installed.

The steel strut - nearly 23-metres long - was delivered in two pieces.

A like-for-like replacement made in Whangārei, it's painted to match the rest of the bridge.

The new strut for the Auckland Harbour Bridge taking shape in a Whangarei workshop. It will be completed and transported by road to Auckland on  Saturday.

The new strut for the Auckland Harbour Bridge taking shape in a Whangārei workshop. Photo: NZTA

Engineers will now carry out tension work, to return the bridge's weight distribution to its usual balance. That work will take several days.

Three lanes are being opened in each direction, however, the two centre lanes will remain closed.

The Transport Agency says it's a significant step towards getting the bridge fully repaired and operational again.

It says the damage caused when a truck was blown over in 120km/h winds on 18 September was unprecedented in the bridge's 61-year history.