18 Aug 2022

Electricity Authority puts restrictions on very large electricity contracts

From Nine To Noon, 9:15 am on 18 August 2022
Tiwai Point aluminium smelter is owned by Rio Tinto, the second largest metals and mining corporation in the world.

Photo: Otago Daily Times / Stephen Jaquiery

The Electricity Authority says very large electricity contracts will only be allowed under certain conditions, under a new interim restriction just announced this morning.

The move targets very large, discounted wholesale contracts such as that of the Tiwai Aluminium Smelter - which it says has the potential to make small consumers pay more.

Last year the Authority estimated the impact of Tiwai's discounted power, could potentially lead to households paying up to $200 extra on their electricity bills each year.

The new restriction will be for nine months, while a proposed permanent amendment is consulted on.

Kathryn speaks with the Electricity Authority's Chief Executive James Stevenson-Wallace.